Today the Southern Gas Corridor project is being successfully implemented. It consists of four parts. The first part is the Shah Deniz gas field. The implementation of Shah Deniz-2 project is already 93 per cent through and it will be fully completed in the coming months. The second part is the South Caucasus gas pipeline connecting Azerbaijan with Georgia. There, too, work is 87 per cent through. The third and the key part is the TANAP gas pipeline. The level of completion here is 77 per cent, and we will celebrate the implementation of this project next year. Finally, the fourth part is TAP, the Trans Adriatic Pipeline. Here the implementation is at the level of 44 per cent. All these four important projects form the Southern Gas Corridor.

From the speech at the Presidential Ceremony of the 22nd World Petroleum Congress
10.07.2017